²ÝÝ®´«Ã½

WSSC stops Piscataway sewage leak; week needed for repairs

The WSSC has stopped a sewage that caused 3.35 million gallons of untreated wastewater to overflow into the Piscataway Creek. (Courtesy WSSC)
The WSSC has stopped a sewage leak that caused 3.35 million gallons of untreated wastewater to overflow into the Piscataway Creek. (Courtesy WSSC)
A full repair for the Piscataway Wastewater Treatment Plant is still at least a week away. (Courtesy WSSC)
Crews were able finish a second set of temporary piping and pumps early Wednesday. (Courtesy WSSC)
The pipe break had no effect on drinking water, the WSSC said; the water and wastewater systems are separate.  (Courtesy WSSC)
(1/4)
The WSSC has stopped a sewage that caused 3.35 million gallons of untreated wastewater to overflow into the Piscataway Creek. (Courtesy WSSC)

WASHINGTON — Sewage from the Piscataway Wastewater Treatment Plant that had been spewing into a creek, then a retention basin, is now being piped into a treatment plant, marking a major milestone in repair efforts.

However, a full repair is still at least a week away. 

A 52-year-old cast iron pressurized sewer main at the plant, in Accokeek, , causing about 3.35 million gallons of untreated wastewater to overflow into the Piscataway Creek, the Washington Suburban Sanitary Commission said.

Crews were able finish a second set of temporary piping and pumps early Wednesday, allowing the sewage to bypass the break and be pumped right into the treatment plant. A third set of temporary pipes are being installed as well.

It took some time to get to the break; it was under a concrete-encased structure that also had high-voltage lines. Those lines had to be de-energized and moved.

The replacement pipe is expected to arrive Friday and will take at least a week to install.

The pipe break had no effect on drinking water, the WSSC said; the water and wastewater systems are separate.

Federal ²ÝÝ®´«Ã½ Network Logo
Log in to your ²ÝÝ®´«Ã½ account for notifications and alerts customized for you.